CONTENTS

Executive Summary. 1

1....... Introduction. 1

1.1        Background. 1

1.2        Scope of the EM&A Report 1

1.3        Organisation Structure. 1

1.4        Contact Information for the Project 2

1.5        Summary of Construction Activities. 2

1.6        Summary of EM&A Programme Requirements. 3

1.7        Status of Statutory Environmental Requirements and Compliance with Further Environmental Permit Conditions. 4

1.8        Impact Prediction Review.. 4

2....... Summary of EM&A Results. 6

2.1        Environmental Site Inspection. 6

2.2        Waste Management Status. 7

2.3        Marine Mammal Monitoring. 8

2.3.1        Monitoring Requirements. 8

2.3.2        Action and Limit Levels for Marine Mammal Monitoring. 9

2.3.3        Monitoring Results. 9

2.4        Marine Mammal Exclusion Zone Monitoring. 10

2.4.1        Monitoring Requirements. 10

2.4.2        Monitoring Results. 10

2.5        Records of Operating Speeds and Marine Travel Routes of Working Vessels. 10

2.6        Implementation Status of Environmental Mitigation Measures. 11

2.7        Summary of Exceedances of the Environmental Quality Performance Limit 11

2.8        Summary of Environmental Complaints, Notification of Summons and Successful Prosecutions. 11

3....... Conclusion and recommendations. 12

 

Annexes

Annex A         Project Organisation

Annex B         Construction Programme

Annex C         Environmental Mitigation Implementation Schedule (EMIS)

Annex D         Status of Statutory Environmental Requirements

Annex E         Cumulative Statistics on Exceedances, Environmental Complaints, Notification of Summons and Successful Prosecutions

 

List of Tables

Table 1.1        Contact Information of Key Personnel 2

Table 1.2        Contact Information for the Project 2

Table 1.3        Major Construction Activities Undertaken in the Reporting Period. 2

Table 1.4        Summary of Status for the EM&A Programme under the Updated EM&A Manual 3

Table 2.1        Key Observations from Site Inspections and Contractor’s Follow-up Actions. 6

Table 2.2        Quantities of Waste Generated for FEP-01/558/2018/A  7

Table 2.3        Quantities of Waste and Marine Sediment Generated for FEP-02/558/2018/A. 7

Table 2.4        Quantities of Waste and Marine Sediment Generated for FEP-03/558/2018/A. 8

Table 2.5        Action and Limit Levels for Marine Mammal Monitoring  9

Table 2.6        Monthly STG and ANI for Finless Porpoise. 10

Table 2.7        Marine Mammal Exclusion Zone Requirements  10

 

List of Figures

Figure 1.1      Indicative Location of Key Project Components

Figure 1.2      Location and Works Area of GRS at BPPS

Figure 1.3      Location and Works Area of GRS at LPS

Figure 2.1      Vessel-based Marine Mammal Survey Location

Figure 2.2      Underwater PAM Survey Location

Figure 2.3      Distribution of Finless Porpoise Sightings in December 2020

 


Executive Summary

To support the increased use of natural gas in Hong Kong from 2020 onwards, Castle Peak Power Company Limited (CAPCO) and The Hongkong Electric Co., Ltd. (HK Electric) have identified that the development of an offshore liquefied natural gas (LNG) receiving terminal in Hong Kong using Floating Storage and Regasification Unit (FSRU) technology (‘the Project’) presents a viable additional gas supply option that will provide energy security through access to competitive gas supplies from world markets.  The Project will involve the construction and operation of an offshore LNG import facility to be located in the southern waters of Hong Kong, a double berth jetty, and subsea pipelines that connect to the gas receiving stations (GRS) at the Black Point Power Station (BPPS) and the Lamma Power Station (LPS).  To demarcate the works between different parties, the following Further Environmental Permits (FEPs) were issued for the Project:

§   the double berth jetty at LNG Terminal under the Hong Kong LNG Terminal Limited (HKLTL), joint venture between CAPCO and HK Electric (FEP-01/558/2018/A) – construction commenced on 27 November 2020;

§   the subsea gas pipeline for the BPPS and the associated GRS in the BPPS under CAPCO (FEP-03/558/2018/A) – construction commenced on 23 September 2020; and

§   the subsea gas pipeline for the LPS and the associated GRS in the LPS under HK Electric (FEP-02/558/2018/A) – construction commenced on 13 December 2020.

This is the Quarterly EM&A Summary Report presenting the EM&A works carried out during the period from 23 September to 31 December 2020 for the Project in accordance with the Updated EM&A Manual.  A summary of monitoring and audit activities conducted in the reporting period is listed below:

Activities

Number of Sessions

For FEP-01/558/2018/A

Marine Mammal Monitoring (vessel-based line transect survey)

6

Passive Acoustic Monitoring (C-POD Deployment)

Ongoing

Marine Mammal Exclusion Zone Monitoring

During percussive piling works for construction of Jetty

Environmental Site Inspection

1

For FEP-03/558/2018/A

Environmental Site Inspection

13

 

Environmental auditing works, including regular site inspections of construction works conducted by the ET, audit of implementation of Waste Management Plan and review of the acceptability of operating speeds and marine travel routes of working vessels were conducted in the reporting period.   No non-compliance of environmental statutory requirements was identified.

Breaches of Action and Limit Levels

Since there were no construction activities conducted in the reporting period requiring impact monitoring of marine water quality in accordance with the Updated EM&A Manual, there were no breaches of Action and Limit Levels for marine water quality monitoring in the reporting period.

As only one month vessel-based marine mammal survey data is available, running quarterly values of encounter rate in terms of STG & ANI were not available for comparison against the Action and Limit Levels.  Therefore, there were no breaches of Action and Limit Levels for marine mammal monitoring in the reporting period. 

Environmental Complaints, Notification of Summons and Successful Prosecution

There were no environmental complaints, notification of summons and successful prosecutions recorded in the reporting period.

Reporting Changes

There were no reporting changes in the reporting period.

Comments, Recommendations and Conclusions for the Quarter

The recommended environmental mitigation measures for the Project were effectively implemented and the EM&A programme undertaken by the ET has effectively monitored the construction activities as well as ensured proper implementation of mitigation measures in the reporting period.

 


1.                 Introduction

1.1            Background

To support the increased use of natural gas in Hong Kong from 2020 onwards, Castle Peak Power Company Limited (CAPCO) and The Hongkong Electric Co., Ltd. (HK Electric) have identified that the development of an offshore liquefied natural gas (LNG) receiving terminal in Hong Kong using Floating Storage and Regasification Unit (FSRU) technology (‘the Project’) presents a viable additional gas supply option that will provide energy security through access to competitive gas supplies from world markets.  The Project will involve the construction and operation of an offshore LNG import facility to be located in the southern waters of Hong Kong, a double berth jetty, and subsea pipelines that connect to the gas receiving stations (GRS) at the Black Point Power Station (BPPS) and the Lamma Power Station (LPS).

The Environmental Impact Assessment (EIA) Report for the Project was submitted to the Environmental Protection Department (EPD) of the HKSAR Government in May 2018. The EIA Report (EIAO Register No. AEIAR-218/2018) was approved by EPD and the associated Environmental Permit (EP) (EP-558/2018) was issued in October 2018. 

An application for Further Environmental Permits (FEPs) were made on 24 December 2019 to demarcate the works between the different parties.  The following FEPs were issued on 17 January 2020 and the EP under EP-558/2018 was surrendered on 5 March 2020. 

§  the double berth jetty at LNG Terminal under the Hong Kong LNG Terminal Limited (HKLTL), joint venture between CAPCO and HK Electric (FEP-01/558/2018/A) ([1]) – construction commenced on 27 November 2020;

§  the subsea gas pipeline for the BPPS and the associated GRS in the BPPS under CAPCO (FEP-03/558/2018/A) ([2]) – construction commenced on 23 September 2020; and

§  the subsea gas pipeline for the LPS and the associated GRS in the LPS under HK Electric (FEP-02/558/2018/A) ([3]) – construction commenced on 13 December 2020.

The location of these components is shown in Figures 1.1, 1.2 and 1.3.

1.2            Scope of the EM&A Report

This is the Quarterly EM&A Summary Report for the Project which summarises the key findings of the EM&A programme during the reporting period from 23 September to 31 December 2020 for the construction works for the Project in accordance with the Updated EM&A Manual and the requirements of the Further Environmental Permits (FEP-01/558/2018/A, FEP-02/558/2018/A & FEP-03/558/2018/A). 

1.3            Organisation Structure

The organisation structure of the Project is shown in Annex A.  The key personnel and contact details are summarised in Table 1.1 below.


 

Table 1.1     Contact Information of Key Personnel

Party

Position

Name

Telephone

CAPCO / HKLTL

(For FEP-01/558/2018/A and FEP-03/558/2018/A)

 

Senior Environmental Manager

Dr Helen Chiu

2596 4116

HK Electric / HKLTL

(For FEP-01/558/2018/A and FEP-02/558/2018/A)

 

Head of Mechanical Engineering, Projects Division

 

Norman Chan

 

3143 3819

 

Environmental Team (ET)

(ERM-Hong Kong, Limited)

 

ET Leader

 

Raymond Chow

 

2271 3114

Independent Environmental Checker (IEC)

(Mott MacDonald Hong Kong Limited)

 

IEC

 

Arthur Lo

 

2828 5757

Contractor

(CNOOC Offshore Oil Engineering Co. Ltd.)

Environmental Manager

H Y Tang

6111 5789

 

Environmental Officer

Kelvin Cheung

9060 1020

1.4            Contact Information for the Project

The contact information for the Project is provided in Table 1.2.  The public can contact the project proponents through the following channel for any enquiries and comments on the environmental monitoring data and related information of the Project.

Table 1.2     Contact Information for the Project

Channel

Contact Information

Email

enquiry@env.hkolng.com

1.5            Summary of Construction Activities

The programme of the construction is shown in Annex B.

As informed by the Contractor, details of the major construction activities undertaken in the reporting period are listed in Table 1.3 below:

Table 1.3     Major Construction Activities Undertaken in the Reporting Period

FEP

Land-based Works

Marine-based Works

FEP-01/558/2018/A

§   Nil

§   Jacket installation

§   Piling installation

FEP-02/558/2018/A

§   Nil

§   Nil (1)

FEP-03/558/2018/A

§   Preparation works at the new GRS (including set-up of site offices, erection of hoarding and mobilisation of wastewater treatment facilities)

§   Excavation for Fire Services, oily water, stormwater drainage diversion and backfilling

§   Excavation for Plate Load Test – Pipe Rack

§   Plate Load Test – Pipe Rack

§   Cable pulling

§   Nil

Remark: (1) The preparation works for marine-based works for FEP-02/558/2018/A (e.g. approval of marine dumping permit) were undertaken in December 2020.  Therefore, no marine-based works for FEP-02/558/2018/A were undertaken in December 2020.  Marine-based works for FEP-02/558/2018/A are expected to commence in January 2021.

1.6            Summary of EM&A Programme Requirements

The status of EM&A Programme for all environmental aspects required under the Updated EM&A Manual are presented in Table 1.4.  As no dredging/jetting operations were undertaken in the reporting period, no marine water quality monitoring was required to be monitored in accordance with the Updated EM&A Manual. The requirements of relevant environmental monitoring, including monitoring parameters, Action and Limit Levels, Event and Action Plan(s), environmental mitigation measures, etc. are presented in Section 2.

Table 1.4   Summary of Status for the EM&A Programme under the Updated EM&A Manual

Aspects

Relevant FEP(s)

Status

Water Quality

Baseline Monitoring

FEP-01/558/2018/A

FEP-02/558/2018/A

FEP-03/558/2018/A

§   Completed

Efficiency of Silt Curtain System

FEP-02/558/2018/A

FEP-03/558/2018/A

§   To be implemented upon early stage of construction works for dredging/jetting operations for FEP-02/558/2018/A (1) and FEP-03/558/2018/A

Construction Phase Monitoring

FEP-02/558/2018/A

FEP-03/558/2018/A

§   To be implemented upon commencement of construction works for dredging/jetting operations for FEP-02/558/2018/A (1) and FEP-03/558/2018/A

Post-Construction Monitoring

FEP-02/558/2018/A

FEP-03/558/2018/A

§   To be implemented upon completion of construction works for the Project

Monitoring for Hydrotesting for the Subsea Gas Pipelines

FEP-02/558/2018/A

FEP-03/558/2018/A

§   To be implemented during hydrotesting for the subsea gas pipelines

First-year of LNG Terminal Operation

FEP-01/558/2018/A

§   To be implemented during LNG Terminal operation

Maintenance Dredging

FEP-01/558/2018/A

§   To be implemented during maintenance dredging

Waste Management

Audit of Waste Management Practice

FEP-01/558/2018/A

FEP-02/558/2018/A

FEP-03/558/2018/A

§   On-going for FEP-01/558/2018/A and FEP-03/558/2018/A

§   To be implemented upon commencement of construction works for FEP-02/558/2018/A (1)

Ecology

Baseline Monitoring (Vessel-based Line Transect Survey and Passive Acoustic Monitoring)

FEP-01/558/2018/A

 

§   Completed

Construction Phase Monitoring (Vessel-based Line Transect Survey and Passive Acoustic Monitoring)

FEP-01/558/2018/A

§   On-going (for percussive piling works for construction of Jetty between July and December)

Post-Construction Monitoring (Vessel-based Line Transect Survey and Passive Acoustic Monitoring)

FEP-01/558/2018/A

§   To be implemented upon completion of construction works for the Project

Marine Mammal Exclusion Zone Monitoring

FEP-01/558/2018/A

FEP-02/558/2018/A

FEP-03/558/2018/A

§   On-going for FEP-01/558/2018/A (marine mammal exclusion zone with 500 m radius)

§   To be implemented when marine dredging / jetting operations (under FEP-02/558/2018/A (1) / FEP-03/558/2018/A) are undertaken

Environmental Site Inspection

Regular Site Inspection

FEP-01/558/2018/A

FEP-02/558/2018/A

FEP-03/558/2018/A

§   On-going for FEP-01/558/2018/A and FEP-03/558/2018/A

§   To be implemented upon commencement of construction works for FEP-02/558/2018/A (1)

Records of Operating Speeds and Marine Travel Routes for Working Vessels

FEP-01/558/2018/A

FEP-02/558/2018/A

FEP-03/558/2018/A

§   On-going for FEP-01/558/2018/A

§   To be implemented upon commencement of marine-based construction works for FEP-02/558/2018/A (1) and FEP-03/558/2018/A

Environmental Log Book

FEP-01/558/2018/A

FEP-02/558/2018/A

FEP-03/558/2018/A

§   On-going

 

Remark: (1) The preparation works for marine-based works for FEP-02/558/2018/A (e.g. approval of marine dumping permit) were undertaken in December 2020.  Therefore, no marine-based works for FEP-02/558/2018/A were undertaken in December 2020.  Marine-based works for FEP-02/558/2018/A are expected to commence in January 2021.

1.7            Status of Statutory Environmental Requirements and Compliance with Further Environmental Permit Conditions

The environmental licenses and permits, including further environmental permits, registration as chemical waste producer, construction noise permits, which were valid in the reporting period.  No non-compliance with environmental statutory requirements, including FEP conditions (status of submission) under the EIA Ordinance was identified.  The status of statutory environmental requirements is presented in Annex D.

1.8            Impact Prediction Review

The potential environmental impacts arising from the major construction activities undertaken in the reporting period provided in Table 1.3 were mainly associated with dust emission from construction activities and stockpiles, waste management, site surface runoff, wastewater discharge and disturbance to marine mammals due to jacket and piling installation works.  There were no breaches of Action and Limit Levels and no non-compliance of environmental statutory requirements identified for the environmental monitoring and auditing works conducted in the reporting period, including regular site inspections of construction works conducted by the ET, audit of implementation of Waste Management Plan and review of the acceptability of operating speeds and marine travel routes of working vessels.  The recommended environmental mitigation measures were properly implemented in the reporting period.  Excessive variation between the EIA study predictions and the EM&A monitoring results was not found and therefore no investigation and follow-up procedures were considered necessary.

The environmental mitigation implementation schedule (EMIS) is presented in Annex C.


 

2.                 Summary of EM&A Results

The EM&A programme for the Project required environmental monitoring for marine water quality and marine mammals as well as environmental site inspections for air quality, construction noise, water quality, waste management, marine ecology, landscape and visual, and hazard to life impacts.  As presented in Section 1.6, environmental site inspections and audit on waste management practice were conducted for FEP-01/558/2018/A and FEP-03/558/2018/A while marine mammal monitoring (i.e. vessel-based line transect survey and passive acoustic monitoring) and marine mammal exclusion zone monitoring with 500 m radius were conducted for FEP-01/558/2018/A during the reporting period, and the findings are presented below.

2.1            Environmental Site Inspection

Regular environmental site inspections were carried out with the Contractor and Project Proponents to confirm the implementation of appropriate environmental protection and pollution control mitigation measures for air quality, construction noise, water quality, waste management, marine ecology, landscape and visual, and hazard to life impacts under the Project.  In the reporting period, 14 environmental site inspections were carried out on 30 September, 7, 14, 21, 28 October, 5, 11, 18, 25 November, 2, 8, 16, 23 and 30 December 2020.  The Independent Environmental Checker (IEC) attended the environmental site inspections as the IEC audits on 30 September, 14 October, 11 November and 16 December 2020 during the reporting period.  The key observations from site inspections and Contractor’s follow-up actions are summarized in Table 2.1.  The environmental mitigation implementation schedule (EMIS) is presented in Annex C.

Table 2.1     Key Observations from Site Inspections and Contractor’s Follow-up Actions

Item

Description

Contractor’s Follow-up Action(s) Taken

FEP-01/558/2018/A

November 2020 (1)

 

N/A

N/A

December 2020

 

Nil observation.

N/A

FEP-03/558/2018/A

September 2020

 

Nil observation.

N/A

October 2020

 

Nil observation.

N/A

November 2020

 

Nil observation.

N/A

December 2020

1

The storage area for chemical waste at GRS in BPPS was not properly secured/locked with an appropriate door/gate.

The storage area for chemical waste at GRS in BPPS was secured/locked with an appropriate door/gate.

Remark: (1) The piling installation vessel for construction of the jetty was under quarantine from 19 November 2020 to 2 December 2020 in Hong Kong waters.  Therefore, no marine-based works for FEP-01/558/2018/A was undertaken in November 2020.  Marine-based works for FEP-01/558/2018/A commenced in December 2020.

2.2            Waste Management Status

Waste management audits were performed with reference to the Waste Management Checklists for the corresponding Waste Management Plans detailed in Annex E of the associated Monthly EM&A Reports during the regular environmental site inspections carried out in the reporting period.  No non-compliance for Contractor’s waste management practices was identified during the audits.

The quantities of different types of waste and marine sediment generated for the three FEPs are summarised in Tables 2.2, 2.3 and 2.4 with reference to the waste flow tables prepared by the Contractor.  General refuse was generated under FEP-01/558/2018/A in the reporting period.  Detailed waste flow tables can be referred to Annex F of the associated Monthly EM&A Reports for the reporting period.

Table 2.2     Quantities of Waste Generated for FEP-01/558/2018/A

Inert C&D Materials Generated (in ‘000m3)

Month/Year

Total Quantity Generated

Hard Rock and Large Broken Concrete

Reused in the Contract

Reused in other Projects

Disposed as Public Fill

Imported Fill

Nov 2020

0

0

0

0

0

0

Dec 2020

0

0

0

0

0

0

C&D Wastes Generated

Month/Year

Metals

(in ‘000kg3)

Paper / Cardboard Packaging

(in ‘000kg3)

Plastics

(in ‘000kg3)

Chemical Waste

Other (e.g. general refuse)

(in ‘000kg)

(in ‘000kg3)

(in ‘000L)

Nov 2020

0

0

0

0

0

0

Dec 2020

0

0

0

0

0

6.910

Table 2.3     Quantities of Waste and Marine Sediment Generated for FEP-02/558/2018/A

Inert C&D Materials Generated (in ‘000m3)

Month/Year

Total Quantity Generated

Hard Rock and Large Broken Concrete

Reused in the Contract

Reused in other Projects

Disposed as Public Fill

Imported Fill

Dec 2020

0

0

0

0

0

0

C&D Wastes Generated

Month/Year

Metals

(in ‘000kg3)

Paper / Cardboard Packaging

(in ‘000kg3)

Plastics

(in ‘000kg3)

Chemical Waste

Other (e.g. general refuse)

(in ‘000kg)

(in ‘000kg3)

(in ‘000L)

Dec 2020

0

0

0

0

0

0

Marine Sediment Generated (in ‘000m3)

Month/Year

Total Quantity of Type L Generated

Total Quantity of Type M Generated

Reused in the Contract

Reused in other Projects

Dec 2020

0

0

0

0

Table 2.4     Quantities of Waste and Marine Sediment Generated for FEP-03/558/2018/A

Inert C&D Materials Generated (in ‘000m3)

Month/Year

Total Quantity Generated

Hard Rock and Large Broken Concrete

Reused in the Contract

Reused in other Projects

Disposed as Public Fill

Imported Fill

Sept 2020

0

0

0

0

0

0

Oct 2020

0

0

0

0

0

0

Nov 2020

0

0

0

0

0

0

Dec 2020

0

0

0

0

0

0

C&D Wastes Generated

Month/Year

Metals

(in ‘000kg3)

Paper / Cardboard Packaging

(in ‘000kg3)

Plastics

(in ‘000kg3)

Chemical Waste

Other (e.g. general refuse)

(in ‘000kg)

(in ‘000kg3)

(in ‘000L)

Sept 2020

0

0

0

0

0

0

Oct 2020

0

0

0

0

0

0

Nov 2020

0

0

0

0

0

0

Dec 2020

0

0

0

0

0

0

Marine Sediment Generated (in ‘000m3)

Month/Year

Total Quantity of Type L Generated

Total Quantity of Type M Generated

Reused in the Contract

Reused in other Projects

Sept 2020

0

0

0

0

Oct 2020

0

0

0

0

Nov 2020

0

0

0

0

Dec 2020

0

0

0

0

2.3            Marine Mammal Monitoring

2.3.1       Monitoring Requirements

2.3.1.1  Vessel-based Line Transect Survey

In accordance with the Updated EM&A Manual, vessel-based marine mammal survey by means of systematic line-transect boat survey was undertaken to examine the distribution and encounter rate of Finless Porpoise (FP) in southern Lantau where a majority of Project construction works would take place.  Survey transects covered three survey areas for line-transect boat surveys, namely Southwest Lantau (SWL), Southeast Lantau (SEL) and Lamma (LM) are presented in Figure 2.1The methodology of the survey is consistent and compatible with that adopted in the EIA baseline surveys as well as the long-term marine mammal monitoring programme conducted by AFCD since 1995 to allow potential comparisons and pooling data for analysis.  Vessel-based line transect marine mammal surveys are conducted during construction of the LNG Terminal.  Each transect line is surveyed twice per month.  The detailed methodology is presented in the Updated EM&A Manual. 

2.3.1.2  Passive Acoustic Monitoring (PAM)

In accordance with the Updated EM&A Manual, underwater PAM survey using C-POD (Cetacean-Porpoise Detector) was conducted at five locations as presented in Figure 2.2.  C-PODs are left in place during construction of the LNG Terminal.  Such duration should allow for a robust record of marine mammal usage of the area to be obtained and allow for the inter-seasonal differences already known for finless porpoises.  The C-PODs have to be serviced every two to four months, subject to review on an as-needed basis, to download accumulated data and replace batteries.

2.3.2       Action and Limit Levels for Marine Mammal Monitoring

The Action and Limit Levels for marine mammal monitoring are established using encounter rate calculated from the six-month baseline vessel-based line transect surveys from the three survey areas as a whole in accordance with the Updated EM&A Manual.  The combined baseline encounter rate will be used to compare with the encounter rate obtained during construction phase monitoring calculated from last three month’s monitoring data (i.e. running quarterly value).  This approach would allow natural seasonal fluctuations in FP encounter rate to be accounted for, and allow data to be reviewed every month such as appropriate remedial actions could be taken timely if the threshold values are triggered.  The Action and Limit Levels are provided in Table 2.5.

Table 2.5     Action and Limit Levels for Marine Mammal Monitoring

Monitoring Area

Action Level

Limit Level

SWL, SEL and LM as a whole

Running quarterly STG < 1.12 & ANI < 2.18 

Two consecutive running quarterly STG < 1.12 & ANI < 2.18

Notes:

STG = Encounter Rate of Number of Porpoise Sightings

ANI = Encounter Rate of Number of Porpoises

Action / Limit Levels will be triggered if both STG and ANI fall below the criteria.

The Event and Action Plan for marine mammal monitoring can be referred to Annex H of the Monthly EM&A Report for December 2020.

2.3.3       Monitoring Results

2.3.3.1  Vessel-based Line Transect Survey

Vessel-based line transect surveys were conducted on 16, 17, 18, 21, 22 and 23 December 2020 durign the reporting period.  A total of 437.98 km of survey effort was collected from the surveys, which included 138.45 km in SWL, 135.53 km in SEL and 164 km in LM.  The total survey effort conducted on primary and secondary lines were 359.98 km and 78.00 km respectively.  50.2% of the total survey effort was conducted in condition of Beaufort Sea State 2 or below with good visibility, and such data can be utilised for the encounter rate analysis.  The raw data of vessel-based line transect surveys can be referred to Annex G of the Monthly EM&A Report for December 2020.

A total four groups of ten FPs were sighted among the three survey areas and all of them were sighted during on-effort search.  Among these FP sightings, a total of three groups of seven FPs were sighted at Beaufort Sea State 2 or below, which can be utilised for encounter rate analysis.

The four porpoise groups were scattered in the southern portion of the three survey areas, which were located to the west of Tai A Chau, the offshore waters in SEL near the works area of the LNG Terminal, to the south of Shek Kwu Chau, and about 5 km to the south of Lamma Island respectively (see Figure 2.3).

The monthly STG and ANI for the combined survey areas from SWL, SEL and LM during the reporting period are summarised in Table 2.6.

Table 2.6     Monthly STG and ANI for Finless Porpoise

Survey Period

On-effort (km)

No. of Sighting

No. of Porpoise

STG

ANI

Dec 2020

219.3

3

7

1.36

3.18

Note: Only data collected at Beaufort Sea State 2 or below were included for encounter rate analysis.

As only one month vessel-based marine mammal survey data is available, running quarterly values of encounter rate in terms of STG & ANI were not available for comparison against the Action and Limit Levels.  Therefore, there were no breaches of Action and Limit Levels for marine mammal monitoring in the reporting period

2.3.3.2  Underwater PAM Survey

Five C-POD units have been deployed at the five locations since the commencement of construction for FEP-01/558/2018/A on 27 November 2020.  These units will be serviced every two to four months, subject to review on an as-needed basis, to download accumulated data and replace batteries.

2.4            Marine Mammal Exclusion Zone Monitoring

2.4.1       Monitoring Requirements

According to Condition 3.7 of FEP-01/558/2018/A, Section 9.11.3 of the approved EIA Report and Section 7 of the Updated EM&A Manual, marine mammal exclusion zone monitoring with 500 m radius is required during the course of percussive piling works for construction of Jetty.  Marine mammal exclusion zone requirements for percussive piling works for construction of Jetty are presented in Table 2.7.

Table 2.7     Marine Mammal Exclusion Zone Requirements

Activity

Exclusion Zone

Requirement

Percussive Piling Works for construction of Jetty

500m

Before percussive piling commences, the exclusion zone must have been continuously clear of marine mammals for 30 minutes.  During percussive piling, if marine mammals are spotted within the exclusion zone, percussive piling works will cease and will not resume until the observer confirms that the zone has been continuously clear of marine mammals for a period of 30 minutes.

2.4.2       Monitoring Results

Marine mammal exclusion zone monitoring with 500 m radius was undertaken during the reporting period when percussive piling works for construction of Jetty was conducted.  No sightings of marine mammals were observed during marine mammal exclusion zone monitoring in the reporting period.

2.5            Records of Operating Speeds and Marine Travel Routes of Working Vessels

The operating speeds and marine travel routes of working vessels for construction of the Project within the reporting period were checked and reviewed.  Four working vessels were used for the construction of Jetty under FEP-01/558/2018/A from 11 to 21 December 2020 during the reporting period.  All these working vessels were operated at a speed lower than 10 knots and followed the relevant marine travel requirements stipulated in the FEP.  No non-compliance on the operating speeds and marine travel routes of working vessels was identified.  Records of operating speeds and marine travel routes of working vessels for construction of the Project provided by the Contractor can be referred to Annex L of the Monthly EM&A Report for December 2020.

2.6            Implementation Status of Environmental Mitigation Measures

A summary of the Environmental Mitigation Implementation Schedule (EMIS) is presented in Annex C.  The necessary mitigation measures were implemented properly for the Project.

2.7            Summary of Exceedances of the Environmental Quality Performance Limit

Since there were no construction activities conducted in the reporting period requiring impact monitoring of marine water quality in accordance with the Updated EM&A Manual, there were no breaches of Action and Limit Levels for marine water quality monitoring in the reporting period.

As only one month vessel-based marine mammal survey data is available, running quarterly values of encounter rate in terms of STG & ANI were not available for comparison against the Action and Limit Levels.  Therefore, there were no breaches of Action and Limit Levels for marine mammal monitoring in the reporting period.

Cumulative statistics on exceedance is provided in Annex E.

2.8            Summary of Environmental Complaints, Notification of Summons and Successful Prosecutions

There were no environmental complaints, notification of summons and successful prosecutions recorded in the reporting period.

Statistics on environmental complaints, notification of summons and successful prosecutions are summarised in Annex E.

 

 


 

3.                 Conclusion and recommendations

This Quarterly EM&A Summary Report presents the key findings of the EM&A works during the reporting period from 23 September to 31 December 2020 for the construction works for the Project in accordance with the Updated EM&A Manual and the requirements of the Further Environmental Permits (FEP-01/558/2018/A, FEP-02/558/2018/A & FEP-03/558/2018/A).

Environmental auditing works, including regular site inspections of construction works conducted by the ET, audit of implementation of Waste Management Plan and review of the acceptability of operating speeds and marine travel routes of working vessels were conducted in the reporting period. No non-compliance of environmental statutory requirements was identified.

Marine mammal monitoring (vessel-based line transect survey and passive acoustic monitoring) was conducted during the reporting period in accordance with the Updated EM&A Manual.  No breaches of Action and Limit Levels were recorded.

There were no environmental complaints, notification of summons and successful prosecutions recorded in the reporting period.

The recommended environmental mitigation measures for the Project were effectively implemented and the EM&A programme undertaken by the ET has effectively monitored the construction activities as well as ensured proper implementation of mitigation measures in the reporting period.


([1])      Application for variation of an environmental permit for FEP-01/558/2018 was undertaken and the latest FEP (FEP-01/558/2018/A) was issued on 6 November 2020. 

([2])      Application for variation of an environmental permit for FEP-03/558/2018 was undertaken and the latest FEP (FEP-03/558/2018/A) was issued on 22 January 2021. 

([3])       Application for variation of an environmental permit for FEP-02/558/2018 was undertaken and the latest FEP (FEP-02/558/2018/A) was issued on 22 December 2020.